Solar project cycle time by stage
Paste finished projects with their milestone dates. Get days per stage, the share spent with third parties, and what held the install start.
A check on your own records. The loaded example is invented: 8 projects with dates chosen for this page, not an industry benchmark. Days are calendar days.
| Result | Value |
|---|---|
| Projects | - |
| Mean contract to PTO (days) | - |
| Median contract to PTO (days) | - |
| Install days as share of all days | - |
| Days with a third party (permit or equipment gate, inspection, PTO) | - |
| Install start held by permit / equipment / tie | - |
| Mean wait after both gates met (days) | - |
By stage (all projects)
| Stage | Held by | Mean days | Share |
|---|
By project
| Project | Total | Gate held by | Gate days | Wait after gates | Install |
|---|
Gate = the later of permit issued and equipment delivered; the other runs in parallel. Wait after gates = install start minus the gate date. The seven segments add up to contract-to-PTO. Nothing leaves your browser.