SolarSoftwares
Book a demo

What Is Grounding (Earthing)?

How we keep reviews fair

Quick answer

Grounding (earthing in UK and IEC documents) connects a PV system’s exposed metal, and in some designs one circuit conductor, to earth. Bonding frames and racking keeps them at one potential in a fault. In the US, a single ground rod needs a second electrode unless it measures 25 ohms or less.

Ready to see how it works?

Tell the SolarSoftwares team which tool you are considering. We reply by email to book your demo.

Book a demo
Jump to a section

Key takeaways

  • Grounding is the US word for a connection to the earth. Earthing is the UK and IEC word.
  • There are two jobs. Equipment grounding bonds exposed metal. System grounding ties one circuit conductor to that bonded system and to earth.
  • The 2012 paper describes 25 ohms or less for one electrode. Your AHJ’s adopted code sets the target.
  • Invented example: a 16 mm rod in 100 ohm-metre soil gives 33.5 ohms at 3 m and 18.6 ohms at 6 m. In 300 ohm-metre soil, 12 m still gives 30.7 ohms.
  • Fall-of-potential tests put the inner stake at about 62% of the way to the outer stake (Metrel, citing IEEE 81-2012). Fluke’s own table uses 60 to 67%.

To keep test records that prove bonding, see the best solar commissioning software.

Grounding and earthing at a glance

Grounding connects metal to the earth. In some designs it also connects one live conductor. Judge it by bonding continuity and by resistance to earth in ohms.

ItemDetail
What it isA deliberate connection to earth. US papers say grounding. IEC-based documents say earthing.
Two jobsEquipment grounding (bond all exposed metal) and system grounding (tie one circuit conductor to it), as Wiles (2012) describes them.
Typical numbersElectrode: 25 ohms or less (2012 paper). Sensitive equipment: 5.0 ohms or less (Fluke Calibration). Bonding conductor: 4 mm² or more (Nordmount).
How it is testedEarth resistance with stakes or clamps. Bonding continuity with a low-resistance tester.
Standard or ruleYour AHJ’s adopted code. Nordmount cites HD-IEC 60364-7-712 for array bonding.
In softwareDesign tools list conductor sizes. Test software reports instrument data. See the software table.

Why does grounding matter for installers?

Grounding conductors appear in plan-set circuit tables. Commissioning must prove the bonding. You may not see a weak connection until a fault happens.

Nordmount says the installer must measure and document bonding continuity before commissioning. Wiles says electrode resistance is rarely measured because it needs specialized equipment. He adds that, as of 2012, many local codes, particularly in the dry Southwest, require two grounding electrodes always. Check your local code, because this comes from his 2012 paper.

For what opens on a fault, see overcurrent protection and arc-fault protection. This page covers the earth connection those devices need. It does not cover ground-fault detection on ungrounded arrays. For conductor sizes, see the wire and conductor sizing page.

What do grounding, earthing and bonding mean?

Grounding and earthing name one idea in two regions. Bonding joins metal parts so they sit at one potential.

TermMeaningSource
Grounding / earthingThe overall idea of connecting a system to the earth. A secondary guide maps the NEC word "grounding" to the IEC word "earthing".Anern guide, updated April 2026
Equipment groundingBonds (electrically connects) all exposed non-current-carrying metal parts.Wiles, October 2012
System groundingOne current-carrying conductor is bonded to the equipment grounding system, which also gives the connection to earth.Wiles, October 2012
Equipment grounding conductor (EGC)"The conductors used to bond the various exposed metal surfaces together" are EGCs.Wiles, October 2012
Grounding electrode conductor (GEC)The conductor that connects to a grounding electrode in contact with the earth.Wiles, October 2012

Then the electrode, bonding and ungrounded terms.

TermMeaningSource
Bonding / equipotential bondingJoins metal parts so they sit at one potential. Nordmount asks for a conductor of at least 4 mm² per array, to an inverter earthing bar.Nordmount document, undated
Grounding electrode"The metallic device used to make contact with the earth".Wiles, October 2012
Grounded PV system"A PV system is defined as a grounded system when one of the DC conductors (either positive or negative) is connected" to the grounding system.Wiles, October 2012
Ungrounded arrayAllowed when the NEC 690.35 requirements are met. Inverters designed for ungrounded systems need no grounding electrode conductor.Wiles, October 2012

An ungrounded array drops system grounding only. The frames still need bonding. Wiles says that before the 2005 NEC, one DC conductor had to be grounded above 50 V. A 1994 Sandia paper says the US and Canada required grounding. It says Europe and Japan opted for an essentially ungrounded system. Rules have changed since that paper.

Nordmount adds that a clamped steel structure is not bonded just by delivery. Assembly does not bond it either. You must check continuity after correct installation and torque.

Two charts: single ground rod resistance against rod length in three invented soils, and fall-of-potential reading error against inner stake position

Figure 1. In example uniform soil, rod length sets whether one rod reaches 25 ohms: 4.2 m at 100 ohm-metres, 15.2 m at 300. In the simple model, a fall-of-potential reading is true near 62% of the way to the outer stake.

How do you measure earth resistance and bonding?

To measure earth resistance, pass a known current through the electrode. Probes in the soil read the voltage. Check bonding on its own, with a low-resistance continuity tester.

Fluke describes the fall-of-potential method this way.

  1. Disconnect the electrode from the site. Connect the tester to it.
  2. Drive two stakes in a straight line away from the electrode. Fluke says 20 m (65 ft) is normally enough.
  3. The tester sends a known current from the electrode to the outer stake. It reads the voltage at the inner stake. Then it applies Ohm’s law.
  4. Move the inner stake 1 m either way and read again. Fluke gives a 30% change as the threshold. If readings differ by more, widen the spacing.

Metrel puts the inner stake at 61.8% of the way from the electrode to the outer stake. It cites IEEE 81-2012, Annex C. Its model assumes equal currents, uniform soil and hemispherical electrodes. Fluke’s table sets the stakes by electrode depth. The last column is our own sum.

Electrode depthInner stakeOuter stakeInner as share of outer
2 m15 m25 m60.0%
3 m20 m30 m66.7%
6 m25 m40 m62.5%
10 m30 m50 m60.0%

Fluke Calibration names four methods. They are stakeless, selective, soil resistivity and fall of potential. It calls the stakeless clamp method preferred when parallel grounds exist and stakes are hard to drive. It gives no pass limit for it.

A four-pin Wenner test gives soil resistivity. Megger prints the formula as 2πaR. Here a is the pin spacing and R the tester reading. Megger calls it "average soil resistivity to a depth equal to the probe spacings".

For bonding, the Fluke SMFT-1000 page lists a protective conductor resistance range of 0.00 to 19.99 ohms. Resolution is 0.01 ohm. Test current is at least 200 mA. The page lists no electrode resistance test.

Does one rod reach 25 ohms? A worked example

One rod reaches 25 ohms only in low-resistivity soil. Soil of 100 ohm-metres needs a rod about 4.2 m long. Soil of 300 ohm-metres needs about 15.2 m. These figures are example and modelled. Rod resistance uses the Dwight formula as EEPower prints it. R = ρ / (2πL) × (ln(4L/a) − 1), with a the rod radius. All inputs are example. The soil is assumed uniform.

CaseSoil (ohm-metres)Wenner reading (2 m spacing)16 mm rod, buried lengthModelled resistance (25 ohms or less?)
A100.07.96 ohms2.4 m (8 ft)40.4 ohms (No)
B100.07.96 ohms3 m33.5 ohms (No)
C100.07.96 ohms6 m18.6 ohms (Yes)
D300.323.9 ohms3 m100.6 ohms (No)
E300.323.9 ohms6 m55.8 ohms (No)
F300.323.9 ohms12 m30.7 ohms (No)

In high-resistivity soil the practical route is a second electrode, or another electrode type. When one electrode does not meet 25 ohms, Wiles describes a second one more than six feet away.

The formula matches EEPower’s own example. Our sum gives 34.7 ohms for a 3 m rod in 100 ohm-metre soil. The rod is 12.7 mm wide. EEPower states about 35 ohms. Doubling the length cuts resistance by about 45%. Raising the diameter from 12.7 to 19.05 mm cuts it by just 6%.

EEPower also warns that frozen upper layers raise resistivity sharply. A reading in one season is not a design value for all seasons. The 25 ohm line is an input here. It is not a rule for your site.

Ground rod resistance calculator

It repeats the table for your own values. The defaults are example.

Open the calculator on its own page

How solar software handles grounding

Of the two software tools and one hand tester below, only Aurora’s Instant Plan Sets lists a grounding conductor size ("EGC size" in the circuit table). None documents electrode resistance. The Fluke tester page covers bonding resistance only.

ToolHandles grounding?
Aurora Solar (Instant Plan Sets)Partly
SolargrafNot stated
Fluke SMFT-1000 with TruTest SolarPartly

Partly: Aurora lists a conductor size, and Fluke lists a bonding resistance test, but neither covers electrode resistance. Not stated: the company page we cite does not say.

  • Aurora Solar (Instant Plan Sets): The Circuit Table list includes "EGC size". The help page does not mention grounding electrode conductors, bonding or electrode resistance. No date shown. Checked October 2026.
  • Solargraf: The SLD and three-line diagram post (no date shown) and the permit settings article (19 March 2026) do not mention grounding, earthing, EGC, GEC or bonding. Checked October 2026.
  • Fluke tester with TruTest Solar: The tester page lists protective conductor resistance and says it works with TruTest data management software. It lists no earth electrode resistance test. No date shown. Checked October 2026.

Tools that draw the single-line diagram carry the conductor sizes. See the best solar SLD software. For test reports, see the commissioning and test report page.

Common mistakes with grounding

FAQs

Is earthing the same as grounding?

In practice, yes. US documents say grounding, and IEC-based documents say earthing. Both name a deliberate connection of a system to the earth. Details differ by code, so follow your AHJ’s adopted edition.

What is the difference between equipment grounding and system grounding?

Equipment grounding bonds exposed metal. System grounding bonds one circuit conductor to that system. An ungrounded array has no system grounding. Bonding means electrically joining metal parts.

What resistance should a ground rod have?

The target is 25 ohms or less for one rod, pipe or plate electrode. Wiles (2012) cites NEC 250.53(A)(2), and a 2023 NEC quote in an ECM code quiz places the 25 ohm exception there too. Fluke Calibration cites 250.56 for 25.0 ohms. Confirm the section in your AHJ’s adopted edition. Fluke Calibration also says NFPA and IEEE recommend 5.0 ohms or less. We did not read those documents.

Do ungrounded PV arrays need earthing?

The frames still need bonding. Nordmount’s IEC-based document asks you to bond the support structure. That applies where bonding is required. It also asks you to measure continuity before commissioning.

Next step: measure the installed electrode and the bonding, then store the results with a tool from the best solar commissioning software list.

Sources

Last updated 30 October 2026. Next scheduled review: 30 January 2027.

See the software on your shortlist.

Tell the SolarSoftwares team what you want in your solar software.

Your request goes by email to the SolarSoftwares team. A demo time is set only after we reply.