SolarSoftwares
Book a demo

What Is a Bill of Quantities (BoQ)?

How we keep reviews fair

Quick answer

Bill of quantities (BoQ, also written BOQ or BQ) is an itemised list of project work and materials with units and quantities. For UK building works, RICS NRM 2 sets the measurement rules. No solar-specific rule set was found. Unlike a bill of materials, it includes work such as piling and testing. Tenderers price it.

Ready to see how it works?

Tell the SolarSoftwares team which tool you are considering. We reply by email to book your demo.

Book a demo
Jump to a section

Key takeaways

  • A BoQ gives measured quantities of work for pricing. A bill of materials lists parts to buy.
  • Our assumed 655.2 kWp plant needs 10 BoQ lines: 1,092 modules give 147 piles, 9,534 m of DC string cable (single conductors) and 81 m of AC cable.
  • Two cable methods agree at 9,534 m. That catches counting slips, not a wrong layout.
  • In our assumed plant, pile spacing of 4.0 m instead of 5.0 m adds 42 piles (28.6%). Seven rows of three tables cut DC cable 53.7% but raise AC cable 254.3%.
  • RatedPower, PVcase and HelioScope document quantity output. No published wastage standard was found.

To pull quantities from a plant layout in software, see the best utility-scale solar design software.

Bill of quantities at a glance

A BoQ turns drawings into a list that every bidder prices the same way.

ItemDetail
FormulaNet quantity = count or measured length taken from the design. Wastage is shown apart from it in our example
Unitsno. for items, m for cable and trench, m³ for excavation. No typical quantities are sourced
Where it mattersTender pricing, cost control and checking changes
Standard or ruleUK building works: RICS NRM 2, October 2021. Building works only, not shown to apply to solar tenders. No solar-specific standard was found
In softwareRatedPower, PVcase and HelioScope document quantity output. See the software table

Why does a bill of quantities matter for installers?

It lets every bidder price the same scope. It also gives the owner a base for checking cost and variations. A missing line is a missing price.

Designing Buildings (a wiki) gives a BoQ as "measured quantities of the items of work identified by the drawings and specifications". For a firm bill, "good financial control should be possible". An approximate bill is "subject to re-measurement", with more cost uncertainty.

An early estimate from a concept layout behaves like an approximate bill (our reading). Re-run the BoQ for each design revision. Priced quantities then feed the capex line. See capex and opex.

How does a BoQ differ from a BoM?

A BoQ lists items of work and materials with measured quantities, so contractors can price it. A BoM lists the parts to buy. Our bill of materials page owns the BoM, its order quantities and its allowances.

The BoQ in our example has lines that are not parts: driven piles, trench excavation and string tests. RatedPower’s glossary page (updated 17 December 2024) also says a BoQ covers the labour a project needs. Tools blur the terms: PVcase’s Bill of Materials export carries piling, cable and grading data.

What sections does a solar BoQ have?

Grouping is the tender’s choice. Our example uses four sections: civil, mechanical, electrical and commissioning.

RatedPower says its BoQ covers main equipment, civil works, electrical systems, monitoring, security and substations. ITI Limited’s price-bid form for a 1,200 kWp plant (undated) has two sections. One has 23 supply-and-install lines. The other has 7 lines, including survey and design and five yearly "CAMC" charges. Piles can sit under civil or mechanical works. The sources do not say which is usual.

The work behind each section has its own page. Cut and fill is in earthworks and grading. Piles are in ground-mount design. Medium-voltage runs are in MV and LV design. Tests are in the commissioning report.

How are quantities measured, and who uses a BoQ?

Measurement follows the rules the tender names. No solar-specific rule set was found, so write the rules into the BoQ itself.

  • UK building works: RICS NRM 2, 2nd edition, October 2021, "provides standard detailed rules for the measurement and description of building works". It is effective from 1 December 2021. It defines a BQ as "a list of items that gives detailed identifying descriptions and firm quantities of the work comprising a contract". The BQ "becomes a contract document". Where a row allows a choice of units, the method should "suit the situation". Designing Buildings (a wiki) says NRM 2 "formally replaced" SMM7 on 1 July 2013. The pages cited do not show whether NRM 2 applies to any solar tender.
  • India, one form: ITI Limited’s price bid has a quantity of 1 for every line, in units of Set, No or Job. Cable lengths sit in the description, for example "900 meter approx.". It says a deviation from its format may lead to rejection. One undated form is not a rule for India.
  • Who prepares it: a cost consultant, often a quantity surveyor, per Designing Buildings. Tenderers price it.

Worked example: a 655.2 kWp ground-mount BoQ

The assumed plant has 1,092 modules on 21 tables. Its BoQ has 10 lines in four sections, with no prices. The layout is a design-stage assumption, and string limits and inverter sizing are not checked. See string sizing and DC to AC ratio.

Input (all assumed)Value
Strings and tables26 modules per string, 2 strings per table, 3 rows of 7 tables: 42 strings, 1,092 modules, 655.2 kWp at 600 W each
Table30.0 m long, 0.5 m gap between tables
Piles5.0 m spacing, a pile at each end: 30.0 / 5.0 = 6 spans, so 7 piles per table
InvertersOne at the west end of each row, 5.0 m from the first table
DC cableEach string has two leads, one at each table end, run along the row to the inverter, plus a 2.0 m tail per lead
AC cableRow 1 inverter to LV board 20.0 m, row pitch 7.0 m, so runs of 20, 27 and 34 m
TrenchDC trench along each row. One AC trench of 34 m. Trench 0.5 m wide, 0.8 m deep
Wastage5% on cable, 2% spare piles
RefItemUnitNet quantityWith wastage
A1 CivilPiles, drivenno.147150 (2%)
A2 CivilCable trench length, DC and ACm688none
A3 CivilTrench excavation volumem³275.2none
B1 MechanicalTables assembledno.21none
B2 MechanicalModules fittedno.1,092none
C1 ElectricalDC string cable, single conductorm9,53410,011 (5%)
C2 ElectricalAC cable, inverter to LV boardm8186 (5%)
C3 ElectricalString invertersno.3none
D1 CommissioningString testsno.42none
D2 CommissioningInverter commissioningno.3none

We keep the BoQ net and show wastage apart, so every bidder prices the same scope. The BoQ leaves out fencing, roads, earthworks, MV, earthing, monitoring and labels. Prices are blank.

Cross-check on C1, two methods.

  • Method A. Adds each string’s two leads: horizontal distance to the inverter plus a 2.0 m tail at each end. One row gives 3,178 m, so three rows give 9,534 m.
  • Method B. Multiplies the conductors in each trench segment by its length. For example, 28 conductors over the first 5 m is 140 m. Table k carries 2 + 4 × (7 − k) conductors, and each 0.5 m gap after it carries 4 × (7 − k). Tails add 56 m per row. It also gives 3,178 m per row.
  • Result. The two methods agreed exactly on every test layout. Both methods read the same layout, so they catch double counting and slips, not a wrong layout. HelioScope’s help says it does not count the vertical height of field segments in wire length. So the tail is an input to set yourself.
Two charts for an assumed 655 kWp ground-mount plant with modules unchanged: conductor count falls with distance from the inverter, and two layout changes move pile, cable and inverter quantities differently.

Figure 1. With modules unchanged, a 4.0 m pile spacing adds 28.6% piles and a 7-row layout cuts DC cable by 53.7% while raising AC cable by 254.3% (assumed inputs).

Effect of two layout changes (each against the base). At 4.0 m spacing, 30.0 / 4.0 = 7.5 rounds up to 8 spans. That is 9 piles per table and 189 in all, 42 more. Spacing falls 20%, yet piles rise 28.6%, because spans round up. With 2% spare that is 193 against 150.

Now take 7 rows of 3 tables, one inverter per row. DC cable falls to 4,410 m. AC cable rises to 287 m, inverters to 7 and trench length to 734 m. Piles and modules do not change. Each of the 7 inverters would serve 93.6 kWp, and inverter sizing is not checked here.

Keep DC and AC cable on separate lines, because they are different cable types. For the loss side of cable length, see wire and conductor sizing.

Solar BoQ cable and pile calculator

Use it to re-run the table above with your own layout and wastage. Its first preset reproduces the table, and two more presets reproduce the layout changes. It warns when an input is blank, negative or out of range. A lone "1,234" or "1.000" is read by the number format you choose, and the tool says how it read it. It checks no spans, voltage drop or soil, and holds no prices.

Open the calculator on its own page

How solar software handles a bill of quantities

Only RatedPower is documented as making a document called a BoQ. Of the 5 tools we read, RatedPower and PVcase give the fullest quantity output, and HelioScope, PVsyst and Aurora Solar give part of it.

SoftwareOutputs quantities?Source and date
RatedPowerYesRatedPower glossary page, updated 17 December 2024. Methodology listed 9 November 2021. Earthworks article undated
PVcase Ground MountYes, as a BOMPVcase help, "Bill of Materials", updated 17 February 2025
HelioScopePartlyHelioScope help, 9 July 2025. Wire-length article, 4 March 2026
PVsystPartlyPVsyst help, installation and operating costs, undated
Aurora SolarPartlyAurora help, updated 15 April 2026

Partly: the page shows some quantities but not a full BoQ. What each page says:

  • RatedPower. Its algorithm produces a detailed BoQ covering equipment, civil works, electrical systems, monitoring, security and substations. Its earthworks article says cut and fill volumes go into the Design Report and the BOQ. Export format not stated. The methodology PDF is not cited.
  • PVcase Ground Mount. Exports XLSX. With piling information and spot levels switched on, it includes piling (table number, number of poles, coordinates, reveal lengths) and spot levels with earth moved. It also has cable lengths between devices with cross-section, and capacity iterations. Units not stated. Examples in metres.
  • HelioScope. A help article covers DC wiring lengths in the Bill of Materials. Lengths use two conductors, in metres in its example. The BOM total matches the report and single line diagram. Resistance loss uses a different total. Only the BOM wire article is cited.
  • PVsyst. Component counts update from the simulation into an editable installation-cost list, priced by piece, by Wc or by m². Cabling not mentioned. The pages cited show no BoQ export.
  • Aurora Solar. Design Mode downloads a Bill of Materials .csv. Racking parts appear only after a racking app design is saved. Piles and civil quantities are not mentioned on the page cited.

For wider comparisons, read the best utility-scale solar design software and best solar design software for EPCs lists. Layout drives quantities: see utility-scale layout optimisation and site plans.

Common mistakes with a BoQ

FAQs

What goes in a solar BoQ?

Each line needs a reference, description, unit and quantity, grouped by section. Our example has 10 lines in four sections. Tenderers then add rates and amounts.

Does a BoQ include prices?

Not until tenderers price it. The BoQ lists quantities. Tenderers add rates and amounts, per Designing Buildings. ITI Limited’s form leaves its price columns blank.

Can I export a BoQ from design software?

Some tools can. RatedPower documents a BoQ. PVcase and HelioScope document a BOM with piling or wire lengths. Check each export against a hand count, as in the cross-check above.

Should wastage be in the BoQ?

Show net quantities and wastage in a separate column unless the tender sets the rule, so every bidder prices the same scope. The pages cited do not say whether a tender wants wastage in the rate or the quantity. Follow the tender’s stated rules.

Next step: To price a BoQ, see the best solar estimating software. For ground-mount layouts, see the best utility-scale solar design software.

Sources

Last updated 30 October 2026. Next scheduled review: 30 January 2027.

See the software on your shortlist.

Tell the SolarSoftwares team what you want in your solar software.

Your request goes by email to the SolarSoftwares team. A demo time is set only after we reply.